Re: Change Start up date after order close

Hello Gaurav,

 

Solution

  • Report MCJB is from Table VIQMEL whereas the Report MCI7 is from Infostructure S070.
  • Because it is from table, your MCJB got corrected instantaneously, whereas you'd notice changes in MCI7 only after S070 update by system the frequency of which is set in OMOS transaction and it is Monthly.
  • Now if you want to see the effect in MCI7 too immediately, you need to update the LIS (S070) now.
  • Read my latest post exactly on this subject: Rebuild PM Infostructures (LIS)
  • I have simulated your case and verified my above reply.

 

 

Regards

KJogeswaraRao