Hi,
Can you please explain me that will the following points impact my MRP for MTS and MTO. If yes then how it will impact? ( Just for your information will run mrp on weekly basis for all plants)
1. Material to material code transfer. That is Material stock A0001 of 100kg to Material stock X0009 of 100kg.
2. Stock adjustment during confirmation. That is adding of additional components apart from bom in confirmation during goods movements.(261 mvt type)
3. Backdated posting against production order. That is my production is done on 1st nov but user due to workload makes the entry in system on 15th nov with posting date as 1st nov.
Regards,
Sun