Have you gone through all the SAP notes mentioned inside the SAP note?
2. The withdrawal quantity is only retained if the just transferred requirements have the same periodicity as the existing requirements (see Note 157739). If weekly requirements, for example, are transferred instead of the existing monthly requirements, the existing withdrawal quantity disappears.
Special case automatic split:
In case of simultaneous automatic split, the respective original period is relevant. If, for example, daily requirements exist, which result from a monthly split, the withdrawal quantity is retained if monthly requirements are transferred again.
Also See modification Note 144513.